US data center map · Texas
Texas data center map
24 campuses · 19,777 MW disclosed · 17 operators
Every Texas data center campus we track, from operating hyperscale sites to projects still in permitting. Each row carries the operator, city and county, power where the operator or a filing has disclosed it, and a public source. Power is shown for 17 of 24 campuses; a tilde marks an estimate. See the methodology for definitions.
Open the full Texas map → Texas battery storage and all projects →
Planned and under construction in Texas
10 Texas campuses are announced, planned or being built, with 16,540 MW of disclosed power between them.
| Campus | Operator | Location | County | Power | Investment | Status | Announced | Year | Source |
|---|---|---|---|---|---|---|---|---|---|
| Fermi America Project Matador | Fermi America | Carson County | Carson County | 11,000 MW | — | Announced | Jun 26, 2025 | 2027 | source ↗ |
| Stargate Shackelford County (Vantage Frontier) | Vantage / Oracle / OpenAI | Shackelford County | Shackelford County | 1,400 MW | $25B | Under construction | Jul 24, 2025 | 2026 | source ↗ |
| IREN Sweetwater 1 | IREN | Sweetwater | Fisher County | 1,400 MW | — | Under construction | — | 2027 | source ↗ |
| Stargate Milam County | OpenAI / SB Energy | Milam County | Milam County | ~1,200 MW | — | Under construction | Sep 23, 2025 | 2028 | source ↗ |
| Meta El Paso | Meta | El Paso | El Paso County | 1,000 MW | $14B | Under construction | Dec 4, 2023 | 2028 | source ↗ |
| Aligned Project Caprock | Aligned Data Centers | Hale County | Hale County | 540 MW | — | Under construction | Feb 27, 2026 | 2027 | source ↗ |
| Google Armstrong County | Armstrong County | Armstrong County | — | — | Planned | 2025 | — | source ↗ | |
| Google Haskell County | Haskell County | Haskell County | — | — | Planned | 2025 | — | source ↗ | |
| Google Pampa (Meitner Energy Center) | Pampa | Gray County | — | — | Under construction | 2026 | — | source ↗ | |
| Google Wilbarger County | Wilbarger County | Wilbarger County | — | — | Planned | Feb 24, 2026 | — | source ↗ |
Free sample — the 100 largest tracked projects
Every column we publish: operator, city, capacity (MW/MWh), status, year online and a public source on each row. Opens straight in Excel or Sheets. No card, no call.
One email with the file. No list, no drip sequence — see our privacy policy.
All Texas data centers
| Campus | Operator | Location | County | Power | Investment | Status | Announced | Year | Source |
|---|---|---|---|---|---|---|---|---|---|
| Fermi America Project Matador | Fermi America | Carson County | Carson County | 11,000 MW | — | Announced | Jun 26, 2025 | 2027 | source ↗ |
| Stargate Shackelford County (Vantage Frontier) | Vantage / Oracle / OpenAI | Shackelford County | Shackelford County | 1,400 MW | $25B | Under construction | Jul 24, 2025 | 2026 | source ↗ |
| IREN Sweetwater 1 | IREN | Sweetwater | Fisher County | 1,400 MW | — | Under construction | — | 2027 | source ↗ |
| Stargate Abilene | Oracle / Crusoe / OpenAI | Abilene | Taylor County | 1,200 MW | — | Operating | Jul 18, 2024 | 2025 | source ↗ |
| Stargate Milam County | OpenAI / SB Energy | Milam County | Milam County | ~1,200 MW | — | Under construction | Sep 23, 2025 | 2028 | source ↗ |
| Meta El Paso | Meta | El Paso | El Paso County | 1,000 MW | $14B | Under construction | Dec 4, 2023 | 2028 | source ↗ |
| Aligned Project Caprock | Aligned Data Centers | Hale County | Hale County | 540 MW | — | Under construction | Feb 27, 2026 | 2027 | source ↗ |
| Microsoft San Antonio | Microsoft | San Antonio | Bexar County | 400 MW | — | Operating | Jan 19, 2007 | 2008 | source ↗ |
| Meta Temple | Meta | Temple | Bell County | 400 MW | — | Operating | Mar 31, 2022 | 2022 | source ↗ |
| Google Midlothian | Midlothian | Ellis County | ~400 MW | — | Operating | Aug 1, 2018 | 2020 | source ↗ | |
| Compass Red Oak | Compass Data Centers | Red Oak | Ellis County | 280 MW | — | Operating | Jan 29, 2020 | 2020 | source ↗ |
| CoreWeave Plano | CoreWeave | Plano | Collin County | 250 MW | — | Operating | Jul 26, 2023 | 2024 | source ↗ |
| Digital Realty Garland | Digital Realty | Garland | Dallas County | 80 MW | — | Operating | Aug 25, 2017 | 2019 | source ↗ |
| CyrusOne San Antonio | CyrusOne | San Antonio | Bexar County | 70 MW | — | Operating | Dec 23, 2011 | 2014 | source ↗ |
| NTT Garland | NTT Global Data Centers | Garland | Dallas County | 65 MW | — | Operating | Aug 20, 2015 | 2018 | source ↗ |
| Lambda Allen | Lambda Labs | Allen | Collin County | 50 MW | — | Operating | — | 2024 | source ↗ |
| Equinix DA11 Dallas | Equinix | Dallas | Dallas County | 42 MW | — | Operating | Feb 21, 2019 | 2020 | source ↗ |
| Meta Fort Worth | Meta | Fort Worth | Tarrant County | — | $1.5B | Operating | May 22, 2015 | — | source ↗ |
| Google Armstrong County | Armstrong County | Armstrong County | — | — | Planned | 2025 | — | source ↗ | |
| Google Haskell County | Haskell County | Haskell County | — | — | Planned | 2025 | — | source ↗ | |
| Google Pampa (Meitner Energy Center) | Pampa | Gray County | — | — | Under construction | 2026 | — | source ↗ | |
| Google Red Oak | Red Oak | Ellis County | — | — | Operating | Aug 31, 2023 | — | source ↗ | |
| Google Wilbarger County | Wilbarger County | Wilbarger County | — | — | Planned | Feb 24, 2026 | — | source ↗ | |
| CoreWeave Denton (Core Scientific) | CoreWeave / Core Scientific | Denton | Denton County | — | — | Operating | — | 2025 | source ↗ |