US data center map · Ohio
Ohio data center map
6 campuses · 1,922 MW disclosed · 5 operators
Every Ohio data center campus we track, from operating hyperscale sites to projects still in permitting. Each row carries the operator, city and county, power where the operator or a filing has disclosed it, and a public source. Power is shown for 4 of 6 campuses; a tilde marks an estimate. See the methodology for definitions.
Open the full Ohio map → Ohio battery storage and all projects →
Planned and under construction in Ohio
2 Ohio campuses are announced, planned or being built, with 0 MW of disclosed power between them.
| Campus | Operator | Location | County | Power | Investment | Status | Announced | Year | Source |
|---|---|---|---|---|---|---|---|---|---|
| Meta Bowling Green | Meta | Bowling Green | Wood County | — | $800M | Under construction | — | — | source ↗ |
| Stargate Lordstown (SoftBank / Foxconn) | SoftBank / OpenAI / Foxconn | Lordstown | Trumbull County | — | — | Planned | Sep 23, 2025 | 2026 | source ↗ |
Free sample — the 100 largest tracked projects
Every column we publish: operator, city, capacity (MW/MWh), status, year online and a public source on each row. Opens straight in Excel or Sheets. No card, no call.
One email with the file. No list, no drip sequence — see our privacy policy.
All Ohio data centers
| Campus | Operator | Location | County | Power | Investment | Status | Announced | Year | Source |
|---|---|---|---|---|---|---|---|---|---|
| Meta Prometheus | Meta | New Albany | Franklin County | 1,000 MW | — | Operating | Aug 15, 2017 | 2025 | source ↗ |
| Google Columbus | Columbus | Franklin County | ~500 MW | — | Operating | Mar 2021 | 2024 | source ↗ | |
| AWS Hilliard | Amazon Web Services | Hilliard | Franklin County | 400 MW | — | Operating | Sep 2014 | 2016 | source ↗ |
| Cologix COL1 Columbus | Cologix | Columbus | Franklin County | 22 MW | — | Operating | Feb 4, 2014 | 2018 | source ↗ |
| Meta Bowling Green | Meta | Bowling Green | Wood County | — | $800M | Under construction | — | — | source ↗ |
| Stargate Lordstown (SoftBank / Foxconn) | SoftBank / OpenAI / Foxconn | Lordstown | Trumbull County | — | — | Planned | Sep 23, 2025 | 2026 | source ↗ |