State profile

Data centers & battery storage in West Virginia

5 tracked projects · 883 MW · 1 data centers, 4 battery (BESS) sites

5
projects
883
MW capacity
1 / 4
data centers / BESS
2
operating

Below is every data center and battery energy storage (BESS) project we track in West Virginia, ranked by capacity. Battery projects are sourced from the federal EIA-860M inventory; data centers are hand-curated with a public source on each entry. See the methodology for details.

View West Virginia on the map →

All West Virginia projects

ProjectOperatorTypeLocationCapacityStatusYearSource
Microsoft CumberlandMicrosoftData centerTucker County600 MWPlanned2028source ↗
Parks Valley Energy LLCParks Valley Energy LLCBESSHampshire150 MWPlanned2027source ↗
Form Energy Iron-Air PilotForm EnergyBESSWeirton85 MWUnder construction2026source ↗
Beech Ridge Energy StorageInvenergy Services LLCBESSGreenbrier32 MWOperating2015source ↗
Laurel Mountain HybridAES Distributed EnergyBESSBarbour16 MWOperating2011source ↗